18th March 2019
If you haven’t been past Henley on Park on Henley Street lately you might want to do a drive by and have a look.
You may be surprised to see how far the building is coming out of the ground! The 3ndfloor slab was poured this week and the builder is moving so fast that we anticipate to have 2 levels poured every month, which means that the building should be at roof cover in June after which lock up and final fit out will commence. Completion is on track for late 2019.